Firmed Projects |
130 m3/d Decore+Poreflon Skid. Client . |
Final Phase with FAT scheduled for 1st week of August.
Punch-list to be completed by End of Dec. |
Tender Phase |
540 m3/d Decore+Poreflon+Phelon Process System. On Clients request, HVAC and Sludge treatment facility is included. |
DOWTEC bid is short-listed for both the 10ppm and 1ppm options. Award of this tender is expected by End-DEC. |
Invited participated as one of consortium partners to bid in Water Flooding Project.
DOWTEC submission is on the provision of salinity controlled injection facility for offshore application. |
DOWTEC proposal was submitted on 24th of Sept. Result of the tender will be known by end of DEC, 2009. |
Upsizing on the current 130m3/day skid to 260m3/d system. |
Cost and design proposal submitted to Client for consideration. |
500k to 1mln litre RW treatment facility with salinity controlled. BOT basis for a Fish Breeding company. |
Quotation submitted to the client. |
Potential Projects |
2500 m3/d Build Operate Own [BOO] scheme for a middle National Oil Company |
Contract is for 10 to 15years. |
100 m3/day gas-water offshore system for Gas Development. |
Discussion with Client was held in mid August. |
Proposed Development of a hydrocarbon storage, processing and distribution facility. |
Quotation submitted and award expected by December 2009. |
Possible 2500 m3/d BOO scheme for Turnkey Company in India |
OPEX model prepared and reviewed. |
New Enquires |
4000 m3/d DECORE+POREFLON for a South American Oil Major |
Discussion with Client was held |
|
Offshore 100-200 m3/d Decore Units for a middle-east client |
Discussion with Client was held |
|
2500 m3/d DECORE System for a middle-east client |
Discussion with Client was held |